Apollo Expeditions to the Moon
AN ALL-UP TEST FOR THE FIRST FLIGHT
In 1964 George Mueller visited Marshall and casually introduced us to his
philosophy of "all-up" testing. To the conservative breed of old rocketeers who had
learned the hard way that it never seemed to pay to introduce more than one major
change between flight tests, George's ideas had an unrealistic ring. Instead of beginning
with a ballasted first-stage flight as in the Saturn I program, adding a live second
stage only after the first stage had proven its flightworthiness, his "all-up" concept was
startling. It meant nothing less than that the very first flight would be conducted with
all three live stages of the giant Saturn V. Moreover, in order to maximize the payoff
of that first flight, George said it should carry a live Apollo command and service
module as payload. The entire flight should be carried through a sophisticated trajectory
that would permit the command module to reenter the atmosphere under conditions
simulating a return from the Moon.
It sounded reckless, but George Mueller's reasoning was impeccable. Water
ballast in lieu of a second and third stage would require much less tank volume than
liquid-hydrogen-fueled stages, so that a rocket tested with only a live first stage would
be much shorter than the final configuration. Its aerodynamic shape and its body
dynamics would thus not be representative. Filling the ballast tanks with liquid hydrogen?
Fine, but then why not burn it as a bonus experiment? And so the arguments
went on until George in the end prevailed.
In retrospect it is clear that without all-up testing the first manned lunar landing
could not have taken place as early as 1969. Before Mueller joined the program, it had
been decided that a total of about 20 sets of Apollo spacecraft and Saturn V rockets
would be needed. Clearly, at least ten unmanned flights with the huge new rocket would
be required before anyone would muster the courage to launch a crew with it. (Even
ten would be a far smaller number than the unmanned launches of Redstones, Atlases,
and Titans that had preceded the first manned Mercury and Gemini flights.) The first
manned Apollo flights would be limited to low Earth orbits. Gradually we would inch
our way closer to the Moon, and flight no. 17, perhaps, would bring the first lunar
landing. That would give us a reserve of three flights, just in case things did not work
as planned.
|
An Instrument Unit being readied for checkout at the IBM facility in Huntsville. A cylinder
22.7 feet across and 3 feet high, the structure
consists of 24 panels with stiffening rings at the
top and bottom. The units that perform the
guidance, control, and telemetry functions for
the Saturn are mounted to the inside of the
cylinder. The foam rubber pads at the top, and
the plastic strips around the outside, are for
protection during manufacture.
|
Mueller changed all this, and his bold telescoping of the overall plan bore
magnificent fruit: With the third Saturn V ever to be launched, Frank Borman's
Apollo 8 crew orbited the Moon on Christmas 1968, and the sixth Saturn V carried
Neil Armstrong's Apollo 11 to the first lunar landing. Even though production was
whittled back to fifteen units, Saturn V's launched a total of two unmanned and ten
manned Apollo missions, plus one Skylab space station. Two uncommitted rockets
went into mothballs.
|
Pressure test during predelivery checkout of
an Instrument Unit at the IBM facility. This IU
was destined for Saturn vehicle 505, which
launched the Apoilo 10 mission. On the launch
pad, the IU, which weighs two tons, sits atop
the third (S-IVB) stage, with the Apollo spacecraft directly above it.
|
But let us go back to 1962. To develop and manufacture the large S-11 and S-IVB
stages, two West Coast contractors required special facilities. A new Government plant
was built at Seal Beach where North American was to build the S-11. S-IVB development
and manufacture was moved into a new Douglas center at Huntington Beach,
while static testing went to Sacramento. The Marshall Center in Huntsville was also
substantially enlarged. A huge new shop building was erected for assembly of the first
three S-IC stages. A large stand was built to static-test the huge stage under the full
7,500,000-pound-thrust of its five F-1 engines. These engines generated no less than
180 million horsepower. As about 1 percent of that energy was converted into noise,
neighborhood windows could be expected to break and plaster rain from ceilings if the
wind was blowing from the wrong direction or the clouds were hanging low. A careful
meteorological monitoring program had to be instituted to permit test runs only under
favorable weather conditions.
Although the most visible and audible signs of Marshall's involvement in Saturn V
development were the monstrous and noisy S-IC engines, equally important work was
done in its Astrionics Laboratory. The Saturn V's airbearing-supported inertial guidance
platform was born there, along with a host of other highly sophisticated electronic
devices. In the Astrionics Simulator Facility, guidance and control aspects of a complete
three-stage flight of the great rocket could be electronically simulated under all
sorts of operating conditions. The supersonic passage of the rocket through a
high-altitude jet stream could be duplicated, for instance, or the sudden failure of one of
the S-11 stage's five engines. The simulator would faithfully display the excursions of the
swivel-mounted rocket engines in response to external wind forces or unsymmetrical loss of
thrust, establishing the dynamic response of the entire rocket and the resulting
structural loads.
|
Super Guppy, bigger sister of the aptly named Pregnant Guppy, was the only airplane in
the world capable of carrying a complete S-IVB stage. Both aircraft were built by John M.
Conroy, who started with the fuselages of two surplus Boeing C-97 Stratocruisers, ballooned out
the upper decks enormously, and hinged the front sections so that they could be folded back
110 degrees. Super Guppy flew smoothly at a 250-mph cruising speed, and its cargo deck
provided a 25-foot clear diameter. Below, a finished S-IVB stage is being unloaded onto a cargo
lift trailer at Kennedy Space Center.
|
The Saturn V's own guidance system would guide the Apollo flights not only to an
interim parking orbit but all the way to translunar injection. It fed position data to the
onboard digital computer, which in turn prepared and sent control signals to the
hydraulic actuators that swiveled the big engines for flight-path control. As propellant
consumption lightened the rocket, and as it traversed the atmosphere at subsonic and
supersonic speeds, the gain settings of these control signals had to vary continuously,
for proper control damping. Serving as the core of the Saturn V's central nervous system,
the computer did many other things too. It served in the computerized prelaunch
checkout procedure of the great rocket, helped calibrate the telemetry transmissions,
activated staging procedures, turned equipment on and off as the flight proceeded
through various speed regimes, and even watched over the cooling system that stabilized
the temperatures of the array of sensitive blackboxes within the IU. So although the
working flight lifetime of the Saturn computer was measured in minutes, it performed
many exacting duties during its short and busy life.
|
Bulky but fragile, huge launch-vehicle stages could not travel by
rail or public road; tunnels, bridges, and low wires would have
dictated endless detours. Right, even a comparatively small Saturn I
wasn't easy to back into its barge at Huntsville. Below, a rocket-laden
barge is escorted by two tugs through Sun-bronzed waters.
The biggest California-built parts of Saturn V voyaged by ship
through the Panama Canal and across the Gulf of Mexico.
|
In planning the lunar mission, why did we plan to stop over in a parking orbit?
The reason was twofold: For one, in case of a malfunction it is much easier and safer
for astronauts to return from Earth orbit than from a high-speed trajectory carrying
them toward the Moon. A parking orbit offers both crew and ground controllers an
opportunity to give the vehicle a thorough once-over before committing it to the long
voyage. Second, there is the consideration of operational flexibility. lf the launch came
off at precisely the right instant, only one trajectory from the launch pad to the Moon
had to be considered. But as there was always the possibility of a last-minute delay it
appeared highly desirable to provide a launch window of reasonable duration. This
meant not only that the launch azimuth hand to be changed, but due to Earth rotation
and to orbital motion the Moon would move to a different position in the sky. A parking
orbit permitted an ideal way to take up the slack: the longer a launch delay, the
shorter the stay in the parking orbit. Restart of the third stage in parking orbit for
translunar injection would take place at almost the same time of day regardless of
launch delays. (As it happened, all but two of the manned Apollo-Saturns lifted off
within tiny fractions of a second of being precisely on time. One was held for weather
and the other was held because of a faulty diode in the ground-support equipment.)
Why was the big rocket so reliable? Saturn V was not overdesigned in the sense
that everything was made needlessly strong and heavy. But great care was devoted to
identifying the real environment in which each part was to work - and "environment"
included accelerations, vibrations, stresses, fatigue loads, pressures, temperatures,
humidity, corrosion, and test cycles prior to launch. Test programs were then conducted
against somewhat more severe conditions than were expected. A methodology was
created to assess each part with a demonstrated reliability figure, such as 0.9999998.
Total rocket reliability would then be the product of all these parts reliabilities, and had
to remain above the figure of 0.990, or 99 percent. Redundant parts were used whenever
necessary to attain this reliability goal.
Marshall built an overall systems simulator on which all major subsystems
of the three-stage rocket could be exercised together. This facility featured replicas of
propellant tanks that could be loaded or unloaded, pressurized or vented, and that duplicated
the pneumatic and hydraulic dynamics involved. Electrically, it simulated the
complete network of the launch vehicle and its interfacing ground support equipment.
|