The Partnership: A History of the Apollo-Soyuz Test Project
Estimating the Costs of a
Mission
[175] The possibility of
flying a joint mission with the Soviets in mid-1975 posed some
interesting problems for Dale Myers' staff in OMSF. When they began
to look at this problem in the fall of 1971, it became apparent that
they would have to make some quick decisions about this
yet-to-be-authorized project if they were to meet the proposed launch
date. MSC would need to start the development work on the docking
module and the docking system in early 1972. And modification of the
CSM should start immediately. Limits on time and money were not the
only problems. OMSF [176] had been advised by
North American Rockwell that beginning in October 1971 the labor
force that had been building the command and service modules (CSMs)
would be reduced. A decision on which CSMs to set aside for an
international rendezvous and docking mission (IRDM) had to be made
quickly. Gilruth had requested that 115 and 115A be completed because
they were of the most recent series of CSMs, with a scientific
instrument module (SIM) bay into which earth resources survey
instruments could be placed. The older 111 CSM was closer to being
ready for launch, but it did not have a SIM bay. CSM 119, the Skylab
backup and rescue spacecraft, could not be allocated to IRDM until
the final Skylab visit, then scheduled for 1974. When the money,
time, and labor issues were balanced against the wishes of the
mission planners, some hard choices had to be made.28
Dale Myers had written to Bob Gilruth four
days before the delegation's departure to Moscow to ask him to look
over a list of "Suggested Guidelines for a Minimum Cost International
Docking Module." This list, prepared by William C. Schneider,
Director of the Skylab Program, reflected OMSF's concern for keeping
the IRDM equipment simple and cost effective. Schneider, drawing from
his experiences with Skylab, suggested that the module be kept as
small as practical and that it be designed with a high safety factor.
He thought it best to follow the Gemini design principle of placing
many systems, particularly wiring, on the outside of the docking
module, thus lowering flammability concerns. At the end of his
recital of 20 items, he said:
The fundamental, you can see, is
keep it simple. Of course, that's how Skylab started in 1966. I have
no solution to maintain that posture other than a generalized
observation that an active Headquarters staff is invaluable in
detecting and controlling policy variations. . . .
I strongly urge that the Skylab system of PRR,
PDR, CDR[*] be adhered to and that short cuts be resisted despite
the immediate lure of maintaining schedule. Each time we've rushed,
cancelled, or hurried by one of these milestones, I've come to regret
it later on.29
Schneider had additional thoughts when it came
to keeping costs to a minimum. He proposed that Marshall Space Flight
Center in Huntsville, Alabama, develop and build the docking module;
according to Schneider they had a proven capability (Saturn launch
vehicles, Apollo telescope mount, multiple docking adapter for
Skylab), existing facilities, and the
[177] proper labor mix. These elements would permit
Marshall to do the job more cheaply than MSC and a contractor.
Furthermore, he believed that with Shuttle Orbiter and Skylab drawing
heavily on Houston's personnel, the docking module development
"probably would not receive much attention or would divert talent
from the other tasks." Schneider could see only one area in which
MSFC might have some difficulties - working with the Flight
Operations Directorate at MSC. To solve that problem, he recommended
that Clifford E. Charlesworth, Eugene F. Kranz, or Glynn Lunney be
transferred to Marshall as "Module Manager to insure a clean
interface."30
Myers sent Schneider's list of 20 guidelines
to Gilruth, with the request that the MSC program plan include these
points, but Schneider's other thoughts about building the docking
module at Marshall were not included.31 Gilruth responded that his team basically agreed with
Schneider's guidelines but countered that these points had already
developed somewhat differently. He enclosed the fourth revision of
the "International Rendezvous and Docking Mission Guidelines and
Constraints Document" for OMSF's perusal. Gilruth told Myers that MSC
"would be glad to discuss the guidelines and the method of
implementation in detail with you and your personnel at the
appropriate time."32 Implicit in his remarks was the idea that the IRDM was
a Houston project. It involved Apollo spacecraft, and MSC knew how to
get the job done. Only Frutkin, the interpreters, and several
secretaries from Washington had joined the Houston delegation that
went to Moscow in November. As the joint effort progressed, Marshall
would be noticeably absent during the negotiations. The Americans
might fly with Salyut, but it was not likely that the Soviets would
rendezvous with Marshall's Skylab. At the November-December meeting,
the Soviets and Americans ruled out a union with the first Skylab; if
such a mission was ever undertaken, it would be with "a Skylab or
another type [of station] to put into orbit after
1975."33
Continuing his dialogue with Gilruth, Myers
sent his comments on the International Rendezvous and Docking Program
Plan to MSC on 14 December 1971. Myers agreed that this document
could serve as the basis for further discussions with the Advanced
Missions Program Office at Headquarters, and he advised Gilruth that
Phil Culbertson's staff would "work with you and your people in
finalizing such a plan." OMSF and Advanced Planning had some specific
items that they wanted Houston to look at again. MSC had proposed
that North American Rockwell undertake developing the docking module
on a sole source procurement plan. Myers' staff questioned the
justification for not soliciting other contractors in open
competition, and they wanted Gilruth to think about competitive
selection. Likewise, OMSF preferred that the prebreathing requirement
during transfer be eliminated, if [178] possible, and that
the planing schedules be further refined.34 Gilruth's staff worked on these problems throughout
December and into February 1972.
MSC's studies of the costs of an International
Rendezvous and Docking Mission and the best way to contract for its
equipment produced an avalanche of paper. Data indicated that such a
mission, using CSM 115 and 115A, would cost in excess of $267 million
and could run nearly as high as $280 million for three docking
modules (one test, one backup, and one flight), seven docking
mechanisms (two flight, four test, and one spare), and experiment
packages. These investigations convinced the Center management that
experience would produce economy in this case, so North American
Rockwell should develop and fabricate the docking module and docking
mechanism. As the builder of the CSM, Rockwell would be able to work
with the command module docking module interface with minimum
difficulty. In addition, they had the Apollo manufacturing equipment
and the necessary labor skills, if the job were begun before the
company started laying off their experienced employees. However, the
ultimate decisions about how much money NASA could afford to allocate
to the mission and who the contractor would be had to come from
Headquarters.35
Dale Myers met with the top
management** on 24 February to discuss the cost of the proposed
docking mission, and they reached three key decisions. First, the
planning effort was to be oriented toward a program that would
include a demonstration flight, but the total program effort was not
to exceed $250 million. Based upon the data already generated, this
ceiling precluded the use of either CSM 115 or 115A. Second, Houston
would have to base its planning on the use of CSM 111 as the likely
flight test vehicle and CSM 119 as a potential backup vehicle
(assuming that it was not flown during Skylab). The budget included
the necessary modifications for CSM 119 to make it flight ready, but
it did not cover the expense of an actual mission based on 119. The
final decision made on 24 February concerned experiments. Since the
111 and 119 service modules did not have scientific instrument bays,
the experiments would have to be much simpler than the earth
resources survey originally proposed. Of the $250 million total, $10
million were allocated for developing experiments that could be
housed in the command and docking modules. No more work on CSM 115
and 115A was contemplated.36
Managing the development of the IRDM hardware
was the task of the Manned Spacecraft Center and its new Director,
Christopher C. Kraft. Effective 14 January 1972, Robert Gilruth had
assumed the position of [179] Director of Key
Personnel Development for NASA, and Deputy Director Kraft had moved
into the number one position. Like his predecessor, Kraft was an
old-timer in the American space program, joining NACA in 1945 and
becoming one of the original members of the Project Mercury team.
Before becoming Gilruth's deputy in 1969, he had been Director of
Flight Operations in Houston. The tasks facing his center in 1972
included preparing for Skylab, developing the multipurpose Space
Shuttle*** and proceeding with Apollo/Salyut - whose teams were
already preparing for the next round of discussions with the Soviets
as Kraft settled into his new office.37
* Preliminary
Requirements Review, Preliminary Design Review, and Critical Design
Review were elements of the NASA spacecraft development cycle, which
had evolved since the early days of Apollo.
** Those present were
Administrator J. C. Fletcher, G. M. Low, W. H. Shapley, and A. W.
Frutkin.
*** The Space Shuttle
had received Presidential approval on 5 Jan. 1972.
28. Myers to George M.
Low, memo, "Need for FY 73 Funding for Post Skylab CSM Mission," 22
Oct. 1971; letter, Myers to Gilruth, 16 Sept. 1971; Myers to Rocco A.
Petrone, memo, "Excess Apollo Flight Hardware," 29 Oct. 1971; Gilruth
to Myers, 25 Mar. 1971, with NASA, MSC, "Post Skylab Missions Summary
Report," 17 Mar. 1971 enclosed; and Gilruth to Myers, 25 Aug. 1971.
This latter letter from Gilruth had argued for completion of 115 and
115A for the IRDM mission and provided specific cost figures. In the
final months of 1971, several briefings were held at MSC on the
subject of how best to use the remaining CSMs. See [MSC], "CSM
Utilization Briefing," 28 Oct. 1971; NASA, MSC, "Utilization of
Apollo Hardware Between Skylab Period and Shuttle Availability," 15
Nov. 1971 and, as revised, 7 Dec. 1971.
29. William C. Schneider
to Myers, memo, "Docking Module," 24 Sept. 1971; and Myers to
Gilruth, 22 Nov. 1971. (HTML
formatter's note: the book, from which this transcription was taken,
omitted a reference to note 29. I have assigned it to the quote on
page 176 of that book.)
30. Schneider to Myers,
memo, "Docking Module," 24 Sept. 1971.
31. Myers to Schneider,
note, 28 Sept. 1971.
32. Gilruth to Myers, 13
Dec. 1971.
33. "Summary of
Results," 29 Nov.-6 Dec. 1971; and Myers to Lunney and Frutkin, memo,
"Sample Summary of Results," 22 Nov. 1971.
34. Myers to Gilruth, 14
Dec. 1971, with enclosure, NASA, MSC, "International Rendezvous and
Docking Mission Program Plan," 21 Sept. 1971.
35. A sample of the
documentation includes [MSC], "International Rendezvous and Docking
Mission Contracting Situation," 23 Dec. 1971; [MSC], "Cost Estimate
for USA/USSR Docking Mission," 7 Jan. 1972; [MSC], "Cost
Assumptions," 27 Jan. 1972; [MSC], "Cost Assumptions," 28 Jan. 1972;
[MSC], "Cost Assumptions," 1 Feb. 1972; [MSC], "CSM/AMDS Status
Briefing," 1 Feb.1972; [MSC], "Program Options," 17 Feb. 1972; NASA,
MSC, "CSM/AMDS Planning Briefing," 8 Mar. 1972; NASA, MSC, "Residual
Apollo Hardware Status," 21 Mar. 1972; NASA, MSC, "Residual Apollo
Hardware Status," 27 Max. 1972; and NASA, MSC, "NR Sustaining:
Currently Negotiated Manpower NR Recommended Sustaining," 14 Mar.
1972.
36. Myers, memo for
record, "Compatible Rendezvous and Docking Study and Potential Flight
Test," 29 Mar. 1972.
37. NASA News Release,
MSC, 72-15, 14 Jan. 1972; and Carol H. Sweeny to distribution, memo,
"Agreements and Action Items from January 11-12, 1972 Meeting
[OMSF]," 31 Jan. 1972.
|