The Partnership: A History of the Apollo-Soyuz Test Project
Chapter 7
Creating a Test Project
[195] The 1972
Nixon-Kosygin accord on space was the watershed in bilateral
discussions between NASA and the Soviet Academy of Sciences. Both the
Low-Keldysh agreement on space science and applications and the test
mission now had the official imprimatur of the two respective
governments. Prior to the Summit, work on the mission had been
managed by NASA's advanced planners, but now that the decision had
been made to fly, the mission planners, the flight operations staff,
and the engineering and development personnel - a large and to a
great extent new team of individuals - took the prime roles.
On 13 June 1972, Dale Myers sent a memorandum
to the Center Directors at Cape Kennedy, Huntsville, and Houston,
outlining the organizational policy decisions that had been made in
preparation for the July plenary meeting with the Soviets. The
Apollo-Soyuz Test Project* was scheduled for mid-1975. With a Saturn IB, the
Americans would launch command and service module (CSM) 111,
reserving CSM 119 as the backup vehicle, if it were not flown during
Skylab.1
Myers advised the centers that effective 11 June the management of
the joint project had been transferred from the Office of Advanced
Missions to the Apollo Program Office. Philip Culbertson and his
staff were directed to assist Rocco A. Petrone and the Apollo team.
In Houston, work on modifying the CSM would be handled by the Apollo
Spacecraft Program Office, under the direction of Owen G. Morris.
Glynn Lunney, who had been assigned as Special Assistant to Morris
the preceding March, was given primary responsibility for overseeing
ASTP. Preparation of the Saturn IB launch vehicle would be carried
out by the Saturn Program Office at the Marshall Space Flight Center
(MSFC), and all launch related activities would be the responsibility
of Kennedy Space Center (KSC).2
During May, René Berglund had suggested
to Chris Kraft that Glynn Lunney be given the responsibility for
managing the ASTP contract with [196] North American
Rockwell. Berglund thought that the task of negotiating with the
Soviets and the spacecraft contractor should be in the hands of a
single individual and organization.3
Lunney seemed to be the logical choice on the American side for
directing the development of the mission and the spacecraft hardware,
as well as managing the U.S. negotiations with the Soviets. At age
36, Lunney had worked with first NACA and then NASA for 17 years,
coming to Houston in 1962. At MSC, Lunney had been a flight director
for the Gemini IX through Gemini
XII missions and filled a similar role
in ten of the Apollo flights, being the lead flight director for the
unmanned AS-201 flight, Apollo
4, which was the first launch of the
Saturn V, and the manned voyages of Apollo 7 and
10. As
Chief of the Flight Directors Office, Lunney gained national
recognition as the leader of the team that worked out the return trip
plans for the Apollo 13 crew following the inflight explosion that
incapacitated the electrical and oxygen systems of their service
module. His performance during those trying days and during the early
negotiations with the Soviets had indicated to the Manned Spacecraft
Center's (MSC's) Director that Lunney was the individual to manage
ASTP for NASA.4
Glynn Lunney and his colleagues worked hard to
structure a basic organizational plan for the next joint meeting.
They hoped that the working procedure developed in Houston at that
summer session would serve as a model for the many meetings that
would follow. Included in Lunney's plans was a proposal for a more
detailed schedule of activities for the next three years and a scheme
for documenting in English and Russian all technical agreements. The
American plan for documentation suggested two series of reports that
would be approved jointly and signed by the appropriate Working Group
members and the Project Technical Directors. ASTP Documents would
codify the basic understandings for conducting the mission, while
Interacting Equipment Documents would record specific technical data
required to ensure compatibility, lay out test plans, and present
hardware specifications and drawings in standardized format.
One presentation, the "Proposed Operating Plan
for US/USSR Meeting on the Apollo/Soyuz Test Project, Houston, Texas,
July, 1972," was typical of the work done in Houston. Besides this
document, which outlined the scope of each working session, tentative
agendas and milestones for the various discussions were also
presented.5
Other pre-meeting documents considered such logistical matters as
transportation between the Soviets' motel and the meeting sites,
plans for refreshments and meals, public affairs arrangements for
photographs of the groups at work, as well as assignments for
interpreters, translators, and Russian language typists. Similar
attention was given to preparing after-work activities for their
Soviet guests.6
[197] Efforts put into
arranging the summer meeting were indicative of the NASA way of
working. As the frequency of the joint negotiations increased and as
the size of the NASA team expanded, so did the amount of paperwork
and the number of briefings and reviews. The pyramid, which reached
its apex in Lunney's office, expanded downward at MSC to include
engineers and specialists in nearly every division. Fifty-eight key
individuals were invited to a 2-hour ASTP briefing on 13 June.
Starting with Director Chris Kraft, his deputy Sigurd Sjoberg, and
their technical assistant George Abbey, the list of invitees included
nearly all those directorate and division chiefs whose organizations
would participate in or support the joint mission. Donald K. Slayton,
Director of Flight Crew Operations, and his deputy Tom Stafford,
attended the briefing, as did Alan Shepard, Chief of the Astronaut
Office. Also present were the chiefs of the Flight Crew Integration,
Crew Training Simulation, and Crew Procedures Divisions. Flight
surgeons and members of the medical research team were on hand. From
the Engineering and Development Directorate came Max Faget,
accompanied by his division chiefs. The Flight Operations Directorate
was represented by flight controllers, computer analysts, landing and
recovery specialists, mission planners, and the flight support team.
In addition to these individuals, Apollo Program Office, Skylab
Program Office, and Science and Applications Directorate
representatives were there.7
This June briefing was a method of getting the
word out; each division chief would in turn inform his subordinates
of the tasks that lay ahead. As those tasks were apportioned, the
number of memoranda and reports would increase dramatically as the
various teams kept their colleagues informed of their progress.
Distribution lists were compiled and periodically revised, and reams
of paper were fed into photocopying machines. All the paper that was
circulated had a purpose - to get the job done and see that all the
work expended was as efficient as possible among such a large group
of people. MSC was now doing what it had been established to do -
plan, develop, and fly a manned mission in space. This briefing was
just one step in ensuring "a more widespread understanding of [the]
project," which Glynn Lunney believed to be "very important to [the]
timely, successful execution" of ASTP.8
While preparations for the joint meeting
progressed, the Apollo Spacecraft Program Office completed
contractual arrangements with North American Rockwell.9
On 30 June, the Procurement Office mailed a letter
contract** to North American containing a statement of work.
[198] Basic tasks included the necessary modifications to
CSM 111, essentially the same type of spacecraft flown on
Apollo 12, 13, and 14, so that it would meet the requirements of ASTP. North
American also agreed under this contract to develop and fabricate the
docking module (DM), docking system, and the support structure for
the DM in the spacecraft lunar module adapter. In conjunction with
the engineering, fabrication, and assembly, the prime contractor was
further assigned major portions of the ground testing for the CSM,
DM, and docking mechanism and a host of other activities that were
necessary to prepare the spacecraft and its systems for the flight
and to check it out after the mission. William B. Bergen, President
of the Aerospace Group, accepted the contract on behalf of North
American Rockwell on 6 July, the day the Soviets
arrived.10
* Although used
unofficially after the May Summit, Apollo-Soyuz Test Project did not
become the official designation for the joint Soviet-American flight
until 30 June 1972.
** This letter contract
was a ninety-day commitment on the part of NASA, issued to start the
described engineering and manufacturing. A negotiated and definitive
contract was issued on 6 Oct. 1972. A fuller account of the
contracting activities is presented in source note No. 10.
1. Dale D. Myers to John
P. Donnelly , memo, "Designation for Joint US/USSR Mission," 5 June
1972; and Donnelly to Myers, memo, "Project Designation," 30 June
1972.
2. Myers to Kurt H.
Debus, Eberhard F. M. Rees, and Christopher C. Kraft, memo, "Apollo
Soyuz Test Project," 13 June 1972; Philip E. Culbertson to Rocco A.
Petrone, memo, "Transfer of Apollo Soyuz Project Responsibility," 9
June 1972; and MSC Announcement 72-31, "Key Personnel Assignment," 2
Mar. 1972.
3. Interview, Leonard S.
Nicholson-Edward C. Ezell, 16 July 1974. Nicholson had discussed the
issue of two-versus-one managers with Berglund prior to the latter's
discussion with Kraft.
4. NASA News Release,
MSC, 68-28, 3 Apr. 1968; Glynn S. Lunney, "Discussion of Several
Problem Areas during the Apollo 12 Operation," paper presented to
AIAA 7th Annual Meeting and Technical Display, Houston, Tex., 19-22
Oct. 1970 (A70-1260); and U.S. Congress, Senate, Committee on
Aeronautical and Space Sciences, Apollo
13 Mission; Hearings, 24 Apr. 1970,
91st Cong., 2nd sess. (Washington, 1970).
5. [NASA, MSC],
"Proposed Operating Plan for US/USSR Meeting on the Apollo/Soyuz Test
Project," July 1972.
6. Caldwell C. Johnson,
"Working Group Meetings Nominal Procedures," 26 June 1972; Johnson,
"Principal Events, July 5 thru July_," 26 June 1972; Johnson,
"Working Group Procedures," 26 June 1972; Johnson, "Status Review,"
28 June 1972; "Proposed Agenda for Joint Meeting of U.S./U.S.S.R.
Working Groups for Compatible Means of Rendezvous and Docking"
[n.d.]; "Outline of Discussion with Dr. Kraft (6/14/72) on
Preparations for July Meeting with the USSR" [n.d.]; Glynn S. Lunney
to Eziaslav Harrin, Tamara Holmes, Dmitri Arensburger, and Dmitry
Zarechnak, memo, "Interpreter's Assignments and Instruction," 5 July
1972; John W. King to Lunney, memo, "Apollo-Soyuz Test Project
Meeting," 20 June 1972; and Lunney to distribution, memo, "Briefing
on Apollo/Soyuz Test," 6 June 1972.
7. Lunney to
distribution, memo, "Briefing on Apollo/Soyuz Test," 6 June 1972,
with attached list of invitees.
8. Ibid.
9. Lunney and Bushuyev
had their usual correspondence exchange before the July meeting;
Konstantin Davydovich Bushuyev to Lunney, 7 June 1972; TWX, Lunney to
Bushuyev, 15 June 1972; and TWX, Bushuyev to Lunney, 22 June
1972.
10. NASA decided to rely
upon North American Rockwell to modify the CSM and build the related
equipment needed for ASTP. The initial IRDM study had been conducted
under a contract change authorization to the original contract,
issued 21 Dec. 1961. The work contemplated for the ASTP mission
required a new contract, and drafting of a new Statement of Work
(SOW) had started in early 1972. A preliminary version of that
document, "Statement of Work for CSM/Advanced Mission Docking
System," 28 Mar. 1972, was distributed throughout OMSF. See
Culbertson to distribution, memo, "Preliminary Statement of Work for
CSM/ Advanced Missions Docking System," 12 Apr. 1972. ASPO had
established an evaluation team to work with the proposed contractor
in evaluating the contract proposal; see James A. McDivitt to
distribution, memo, "Designation of Evaluation Team for ASTM
(Apollo/Salyut Test Mission) Contract Proposal," 11 Apr. 1972.
Meanwhile, Terrence Heil had prepared a procurement plan,
"Development of Command and Service Module/Advanced Missions Docking
Systems (CSM/AMDS)," on 2 Mar., which among other things contained a
justification for a noncompetitive procurement. Culbertson described
the reasons for selecting NAR in interview, Culbertson-Ezell, 5 May
1975. This procurement plan was approved by Kraft on 29 Mar. and
forwarded to Headquarters. Following the May summit, the SOW was
changed where necessary to reflect the shift from Salyut to Soyuz,
and a letter contract was issued on 30 June. See letter contract,
Heil to North American Rockwell Corp., Space Division, Contract
NAS9-13100, 30 June 1972. This contract was accepted by NAR on 6 July
and scheduled to run for 90 days; a definitive contract was to be
negotiated by 29 Sept. Because there was a short delay and that
definitive contract was not issued until 6 Oct., Kraft sought a
30-day extension on 22 Sept. See TWX, Kraft to Dale D. Myers, 22
Sept. 1972; and TWX, Myers to Kraft, 28 Sept. 1972. The definitive
contract, issued on 6 Oct., was also numbered NAS9-13100.
|