The Partnership: A History of the Apollo-Soyuz Test Project
Preliminary Systems Review (Stage
2)
Working Group 3 tests of the two-fifths-scale
model and the second part of the Preliminary Systems Review for the
docking system was the last joint activity scheduled for 1972. The
Americans arrived in Moscow on the 6th of December and worked through
the 15th. MSC specialists were becoming seasoned travelers. During
the October meeting in Moscow, most of the Americans had been
infected by an intestinal parasite, which severely debilitated some
of them after their return home. As a consequence, the team that went
to the U.S.S.R. in December took along some pans in which they could
boil their drinking water, hot plates, and some American style
food-crackers, peanut butter, and canned dinners - to which their
stomachs were more accustomed. With these supplementary rations and
other items obtained from the American Embassy commissary, Don Wade
reported that his team returned in much better health. Group 3's work
went better than it had in October, too.52
Wade said that the Soviets were well prepared
for the meeting. They had a team ready to begin the tests of the
two-fifth's-scale docking systems. And following Lunney's suggestion,
the Soviets provided the Americans with English and Russian versions
of the materials they planned to discuss. There were some minor
problems along the way, but all in all the trip was very successful.
The PSR went especially smoothly, with the changes in the engineering
drawings being studied and accepted by Syromyatnikov and Wade, who in
turn recommended their acceptance by the Technical Directors at their
March 1973 meeting.53
Testing the scale models at the Institute of
Space Research in Moscow [216] went equally well.
In his report to Chris Kraft, Lunney pointed out that these tests had
indicated compatibility of the two systems in both the active and
passive modes and that Working Group 3 had anticipated the minor
problems experienced during the exercise and had already accounted
for them in the revised drawings. Summarizing, Lunney said:
The meeting is considered to be a
very successful one and, while we haven't placed a great deal of
importance on the results of the model tests, I believe the
accomplishment of this first major hardware related milestone on
schedule is in itself significant. We have identified no major
problems and are proceeding on schedule.54
Critics and supporters alike were surprised at
the basically cooperative attitude of the Soviets and the progress
being made toward the joint flight. There had been some frustrating
moments for Glynn Lunney and his associates, and there would be times
of tension and disagreement in the future, but how things had changed
since the days of October 1957 or April 1961. Given the background of
competition that had produced Sputnik, Gagarin's orbital mission, and
the American resolve to beat the Soviets to the moon, the cooperative
aspects of ASTP boggled some minds. One pair of critical writers
found it all hard to believe:
Subsequent meetings were reported
as going equally well. This applied both to specific "Working
Groups," which met with increasing frequency either in the USSR or
the US, and to large "plenary" meetings of full delegations from both
sides concerned with the project. Within the compass of the ASTP
project itself, these meetings were marked by exchanges of technical
data and information, as well as a degree of personal contacts among
the specialists involved almost without precedent in US-Soviet
relations including those of the war-time alliance.55
The Soviets and Americans accomplished many
things, but they still faced a multitude of tasks.
52. Wade to Lunney,
memo, "Working Group #3 Debriefing Notes for the December 7-15, 1972,
Meeting in Moscow" [drafted 20 Dec. 1972]. Dr. W. R. Hawkins, who
accompanied the Working Groups in Oct. 1972, said that the parasite
encountered was diagnosed as Giardia
lamblia, which produces intestinal
distress and severe diarrhea. The U.S. Public Health Service
concluded that the NASA team probably contracted the parasite in the
drinking water during their visit to Leningrad; interview (via
telephone), W. R. Hawkins-Ezell, 3 Sept. 1975.
53. Wade to Lunney,
memo, "Working Group #3 Debriefing Notes for the December 7-15, 1972,
Meeting in Moscow" [drafted 20 Dec. 1972]; and "Apollo/Soyuz Test
Project: Minutes of Meeting on Assuring Compatibility of Docking
Systems, Working Group 3," 6-16 Dec. 1972.
54. Lunney to Kraft,
memo, "Summary Report on Results of ASTP Working Group 3 Meeting in
Moscow," 21 Dec. 1972, enclosing "Summary of ASTP Working Group 3
Meeting," 6-16 Dec. 1972.
55. Dodd L. Harvey and
Linda C. Ciccoritti, U.S.-Soviet
Cooperation in Space (Coral Gables,
Fla., 1974), p. 246.
|