The Partnership: A History of the Apollo-Soyuz Test Project
Testing Hardware
While the crews were beginning to study
spacecraft systems related to the mission, progress continued in
readying the hardware they would ultimately fly. From 16 September to
24 December, Working Group 3 conducted tests with the developmental
version of the docking system. This first piece of full scale
equipment had been built from the engineering drawings as they had
been perfected to that point, and while it was still far from being a
flight-ready item, this version of the docking system was subjected
to careful analytical and operational scrutiny on the computer-driven
Dynamic Docking System Simulator (DDTS). Housed in the JSC Structures
and Mechanics Laboratory, the DDTS was capable of duplicating the
most severe impacts and thermal conditions that could be anticipated
when the docking systems were brought together in space. The test
program consisted of 236 test runs, which subjected the American and
Soviet gear to [258] temperature ranges
of -50° to 70° centigrade and to the active and passive
modes.
A team of eight Soviet specialists, led by V.
S. Syromyatnikov and Ye. G. Bobrov, worked with the regulars of Group
3, plus the test personnel in George E. Griffith's Structural Test
Branch, computer people from the Spacecraft Systems Laboratory, and
contractor employees who operated the DDTS. The extremely complex
facility had been completed just before the Soviet team arrived, and
some initial problems were encountered with the simulator, taking
time away from the scheduled testing. According to Bob White, who had
overall responsibility for the tests, "this caused team members from
both countries to dedicate many extra hours at night and on weekends
for make-up testing. Everyone worked admirably without complaining
and a strong sense of mutual respect became discernible." Although
the schedule was very demanding, one weekend was set aside for a
private tour of the State Capitol and the Governor's office in
Austin, as well as the engineering college and the Lyndon B. Johnson
Library at the University of Texas.
During this fourteen-week evaluation process,
a number of minor changes were incorporated into the design. But
since there were no failures or major problems with either the U.S.
or U.S.S.R. docking system, manufacture of the flight hardware could
proceed on schedule. While the flight and backup systems would be
subjected to a much more rigorous quality assurance program while
being manufactured, the dynamic docking tests of the prototype system
had been an essential step in defining the characteristics of that
production equipment. With all the extra work completed, the Soviets
departed on Christmas day, and many of the Americans, accompanied by
their families, traveled to the Houston Intercontinental Airport to
wish their friends a safe journey.32
During mid-January joint meetings held in
Houston, the Soviets participated in tests of the docking module
environmental control systems (ECS). As in the case of the
development of the docking system, the breadboard version of the
docking module ECS was designed to check out...
Interior view of environmental control
system breadboard. Test specialist Tom Wilks prepares for test of the
system under simulated space conditions.
[259] the operational and
functional characteristics of the prototype equipment prior to
fabrication of flight hardware. Although the test hardware was
different in appearance from the final docking module and although
the Apollo and Soyuz transfer tunnels were simulated by two pressure
vessels, the ECS test hardware functioned like the real thing. The
ECS breadboard was placed in the Life Systems Laboratory vacuum
chamber, a horizontal cylinder 2.44 meters in diameter and 5.8 meters
long. The chamber, divided by a bulkhead into two compartments,
consisted of a manlock passageway and a test chamber to house the
test article. Like most test facilities at JSC, the vacuum chamber
was equipped with a closed circuit television system, which permitted
remote viewing of the manlock compartment, the breadboard ECS, and
the test chamber interior, and also equipped with a multi-channel
intercommunications system, which linked all test personnel.
The joint tests, which ran from 16-23 January,
were divided into two major categories - manned simulated mission
tests and unmanned functional performance tests. During the manned
tests conducted on 16 January, the performance of the system was
demonstrated by simulating three transfers, during which the docking
module environment reflected extreme situations that were not likely
to occur during flight. By testing extreme cases, the suitability of
the systems was scrutinized and the acceptability of manned operation
under low or high oxygen pressures was determined. Later, unmanned
functional performance testing was conducted to establish the leakage
rates for the test chamber and to verify the major failure protection
systems included in the docking module ECS. Results from these
exercises indicated that the environmental control system met all the
design specifications and that the transfer procedures were adequate
in both normal and emergency situations. In addition, all of the
safety equipment, such as the overpressure valve, performed
successfully.33
Next came familiarization training for the
American ASTP crews with this hardware. After the completion of the
last Skylab visit on 8 February, all of the crewmembers were given
briefings on the docking module systems. On 25 February, they
participated in a two-hour walk-through of the ECS...
Docking systems installed on a
simulator.
[260] ....breadboard and
test setup. The following day, after a four-hour Skylab debriefing in
which all ten ASTP crewmen were involved, Brand and Evans took the
first turn in the vacuum chamber to learn the ECS equipment and to
practice transfer. Stafford and Slayton went through the same
four-hour experience the next day, as did Bean and Lousma on 5 March.
The crews were also increasing the number of training hours spent in
the command module procedures simulator and command module simulator.
And if that were not enough, they had met on the 4th with their new
Russian instructors and had begun a new series of intensive
lessons.34
Slayton and Stafford had not resumed their
language studies after their last return from Star City, and the
other crewmembers needed to begin learning Russian. During the
November 1973 training sessions in the Soviet Union, the U.S.
astronauts had discovered that the cosmonauts had made significant
progress in their English studies. When Stafford asked Leonov how
they had made such advances, he told the Americans that each member
of the Soviet prime crew had his own individual instructors. They
were studying language six to eight hours a day. Stafford cabled
Washington through the American Embassy in Moscow and requested that
the State Department's Foreign Service Institute provide the
astronauts with two full-time Russian instructors starting early
January. Stafford later told Chris Kraft that the American crew was
going to look bad if its members were unable to communicate
satisfactorily with their Soviet counterparts. They must get some
full-time language training.35
Given the need for additional instruction and
the desire to keep abreast of the progress being made by the Soviets,
Nick Timacheff was authorized to locate professional teachers who
could work with the astronauts. Timacheff screened a number of
applicants during the post-Christmas convention of Slavic language
professionals in Chicago. Four teachers were selected for their
knowledge of contemporary vernacular Russian as opposed to the
language as spoken by diplomats. Anatole A. Forostenko, Vasil
Kiostun, James D. Flannery, and Nina N. Horner would learn as they
taught, since they would have to teach their students the Russian
equivalents of NASA's aerospace jargon. While Nina Horner
concentrated on lengthy hours of classroom instruction, Forostenko,
Kostun, and Flannery accompanied the astronauts on many trips and
worked out with them in the gym in an effort to keep them thinking
Russian - even when they were playing handball or lifting weights.
Starting on 4 March, the prime and backup crewmembers received 3 or
more hours of language instruction daily, five days a week. In their
spare time, if they were not flying T-38s to keep their reactions
sharp, they had cassette tape recorders by their sides to keep their
ears sharp.
While the crewmembers studied, Working Group 5
specialists led by Walt Guy went to Moscow to observe testing of the
modified Soyuz life [261] support system.
American technicians visited a Red Air Force base about 6 kilometers
from Star City where the Soviets had their vacuum test chambers. The
main test chamber used for the Soyuz tests was composed of a
horizontal manlock and a vertical cylinder that was sufficiently
large to hold a stacked descent vehicle, orbital module, and docking
module simulator. Guy noted the similarities and differences between
this test facility and the one in Houston, a major difference being
the lack of communications headsets among the test personnel. He
commended, "The close proximity of the test crew to each other and
the exceptionally quiet test environment . . . made the public
address system quite acceptable."
Among the systems evaluated during the tests
were those for lowering and raising the Soyuz cabin pressure to
determine the effect that transferring men from one spacecraft to
another had on the gas composition under normal and abnormal
conditions. Guy, Group 5's American chairman, reported later that he
came away from the tests with no doubts that the Soviet ECS would
work satisfactorily. He had been somewhat concerned about the basic
uncontrollability of the chemical bed oxygen system, but after
prolonged simulated transfers into the docking module mockup followed
by flushing all the docking module gases into Soyuz, the Soviet ECS
proved capable of removing the carbon dioxide and other effluents
from the atmosphere. At the Americans' request, the trial runs
involving four men were longer than the transfers planned for the
actual mission; therefore, this was an excellent evaluation of its
capabilities. After working with the Soviets in their laboratory, the
U.S. team grew confident that there would be no problems with the
U.S.S.R. equipment. This was exactly why Glynn Lunney had wanted his
men to participate in such activities.36
32. Interview, Robert D.
White-Ezell, 30 Sept. 1975; "Apollo Soyuz Test Project, Results of
Apollo Soyuz Docking Systems Development Tests," IED 50013, 25 Dec.
1973; NASA, MSC, "E&D Weekly Activity Report," 9-15 Jan. 1974;
and White to James M. Grimwood, memo, "Comments on E. C. Ezell's
Draft Manuscript of the ASTP History," 6 Jan. 1976.
33. "U.S.A. Docking
Module Environmental Control System Breadboard Testing Quick-Look
Report," in "Minutes, Working Group 5," 14-25 Jan. 1974.
34. Data given by
Brzezinski, 23 Sept. 1975; and interview (via telephone), Walter W.
Guy-Ezell, 1 Oct. 1975.
35. Interview, Thomas P.
Stafford-Ezell, 6 Apr. 1976.
36. "Integrated Testing
of the Soyuz Life Support System," 11-22 Mar. 1974; "Apollo Soyuz
Test Project, Minutes, Working Group 5," 11-22 Mar. 1974; and
interview (via telephone), Guy- Ezell, 1 Oct. 1975.
|