The Partnership: A History of the Apollo-Soyuz Test Project
Compatible Atmospheres
Ed Smylie and his NASA colleagues working on
environmental control problems with the Soviets were quite satisfied
with their progress. Ilya Vladimirovich Lavrov was present at the
Moscow sessions, and it was apparent to the Americans that he had
sparked considerable activity on his team's part since the July
meeting. With few preliminaries, the October talks tackled the
question of spacecraft pressures. The Apollo command module
[211] would continue to operate at its standard pressure,
258 mm Hg. But at the Soviets' suggestion, the pressure of the Soyuz
would be lowered during the docked portion of the flight to eliminate
lengthy pre-breathing periods. While the "most rational decision to
make would have been to utilize the same atmosphere with regard to
total pressure and partial pressures of oxygen," the Apollo could not
have an operational pressure higher than 325 millimeters, and the
Soyuz for reasons of fire safety could not have an oxygen content
higher than 40 percent. In addition to greatly simplifying the
onboard hardware and equipment with which the crews would work, this
important Soviet design concession also meant that the transfers
between the two ships would be easier, reducing time and
procedures.39
Group 5 also discussed the Soyuz life support
system and modifications that would be required to lower pressure
during the joint phase of the mission. Lavrov indicated that the
Soviets had put aside all considerations of using a pressurized
oxygen system and instead would modify the existing potassium
superoxide oxygen generating system. In addition, they said that they
would develop an emergency pressurization system as NASA had
suggested. At this meeting, the Americans finally understood that
this capability had not been present on earlier Soyuz flights and
that in fact the Soviets had never carried any pressurized gases on
their spacecraft.40
The specialists also discussed such
contingency situations as extravehicular transfer and the return of
mixed crews. After reviewing the life support systems of both
spacecraft, they came to the conclusion that there was no real need
to consider external transfer on this mission, thus eliminating the
need for special equipment related to space suits. Return of a
crewmember from one nation in the spacecraft of the other was
considered a possibility in an emergency situation, but it would have
to be accomplished without the use of any supplementary equipment.
The Soviets requested more time to study this contingency and agreed
to report back in March 1973. Lavrov also indicated that they had
definite plans for vacuum chamber tests (similar to the American
tests of an early breadboard mockup of the DM) of an orbital module
docking module combination. The Americans said they would provide the
Soviet team with drawings so they could build a DM boilerplate model
for these tests.41
The meeting in Moscow had gone well. From his
vantage point on 25 October, Lunney said at a combined debriefing
session and ASTP staff meeting in Houston that he had been pleased
with their progress. He noted that the Soviets had been well
prepared, providing adequate translators, interpreters, and general
logistical support for the gathering. Reporting on future activities,
he said that Groups 2 and 4 would meet in November, Group 3 would
hold tests in December, and the next plenary sessions were scheduled
for March 1973 in Houston.42
[212] After getting back
to Texas, Lunney and his ASTP team prepared for two major reviews of
hardware design with North American Rockwell. On 8 November, the
Critical Design Review (CDR) for CSM 111 and the Preliminary Design
Review for the docking module and docking system were convened at the
contractor's Downey factory. Basically, the CDR was held to conduct a
detailed check on the CSM engineering specifications and drawings
prior to their release to the production engineers who would then
oversee the manufacturing and assembly. The PDR for the docking
module and the docking system was another in the series of basic
checks on the detailed design tasks related to those pieces of flight
hardware. For these reviews, there were 24 teams, each of which was
co-captained by a NASA and a contractor employee. Following two days
of study, Lunney sat as chairman of a Design Review Board, which met
at 8:30 a.m. on the 10th.* 43 While these reviews were in process, Rocco Petrone
briefed the Office of Manned Space Flight (OMSF) Management Council
on the major accomplishments of the October trip to Moscow and Ed
Smith and R. H. Dietz prepared their Working Groups for the sessions
slated to begin on 24 November.44
* The members of the
board were as follows: from MSC, G. S. Lunney, T. P. Stafford, D. R.
Scott, R. A. Colonna, F. Miller, R. P. Burt, E. W. Sievers, and A.
Dennett; and from Rockwell, G. Merrick, E. P. Smith, and C.
Helms.
39. "Minutes of Working
Group No. 5," 9-20 Oct. 1972, in "Minutes of Joint Meeting"; and
Lunney, "Minutes, ASTP Staff Meeting, October 25, 1972," 30 Oct.
1972.
40. Lunney, "Minutes,
ASTP Staff Meeting, October 25, 1972," 30 Oct. 1972.
41. Ibid.; and "Minutes
of Working Group No. 5," 9-20 Oct. 1972, in "Minutes of Joint
Meeting."
42. Lunney, "Minutes,
ASTP Staff Meeting, October 25, 1972," 30 Oct. 1972.
43. NASA, MSC, "Minutes
of Meeting, ASTP CSM 111 Critical Design Review; DM-DS Preliminary
Design Review," 8-10 Nov. 1972; and Morris to distribution, memo,
"Apollo Soyuz Test Project (ASTP) Design Review," 2 Nov. 1972.
44. NASA, OMSF, "Manned
Space Flight Management Council," 8 Nov. 1972.
|